A UPS for server cabinets and tills: how many minutes you actually need
When choosing a UPS for server equipment, most people look at the power rating first and the price second. The question that comes before both is different: what has to happen when the power goes, and how long does that take? Answer that and you know how many minutes the UPS must deliver, which devices belong on it and which do not. This is how we work it out with clients.
A UPS has one of three jobs: riding through short interruptions, shutting everything down cleanly, or bridging until a generator starts. The number of minutes follows from that choice.
Work back from the shutdown sequence: measure how long a clean shutdown takes, add the delay and a margin for ageing batteries, and only then choose the rating.
A UPS without a working link to the servers rides through the outage and then lets everything drop hard. Test it, and replace the batteries by date.
A UPS for server equipment has one job, and you choose it first
A UPS can do three things, and they are three different designs:
- Riding through short interruptions and dips. Many outages last seconds: a voltage dip or a brief interruption before the mains returns. Without a UPS everything restarts and something occasionally gets damaged; with a small one nobody notices.
- Shutting down cleanly. If the outage lasts longer, the UPS shuts down servers, storage and the rest in the right order before the battery runs out. No corrupt database, no storage spending days checking itself on restart.
- Bridging to the generator. If there is a generator, the UPS only has to cover the time until it has started and is delivering stable power.
What is not on the list is “keep working as long as possible”. Working on without a generator sounds attractive, but laptops carry on on their own batteries while lighting and cooling do not, and whether the connection outside your building stays up depends on the operator. So choose deliberately between shutting down and bridging; the difference in batteries is large.
What belongs on the UPS, and what must come off
A UPS fills up faster than you would think, usually with devices that do not belong on it. Make a list per outlet.
- On: the firewall and router, the operator’s device where the internet connection comes in, the core switch, the servers, the NAS or storage, and everything needed to pass the shutdown signal around.
- A deliberate choice: PoE switches for phones, access points and cameras. They draw a lot of power, and whether the phones must keep working during an outage is a decision, not a default.
- Off: laser printers (their warm-up surge can trip a UPS), heaters, coffee machines and screens nobody needs when everything is shutting down.
Many UPS units have outlets that only offer surge protection and do not run on battery. Know which ones they are before you plug anything in.
How many minutes: work back from the shutdown sequence
The right number of minutes is not a feeling but a sum. For a UPS that must shut down cleanly:
- The delay. How long the UPS waits before starting the shutdown. Too short, and every brief outage switches your environment off; too long, and too little battery is left.
- The shutdown duration. How long it really takes to shut down all virtual machines, the hosts and finally the storage. Measure it once; it is often longer than expected.
- A margin for ageing. At the end of its life a battery delivers considerably less than when new. Calculate with the old battery, not the new one.
For a UPS bridging to a generator: the start and transfer time stated by the generator supplier, with a margin for a generator that does not start at the first attempt.
The rating comes after that, and you measure it in watts. A UPS carries two figures, VA and watts, and equipment draws watts. Do not add up the labels; measure what actually flows, and put that against the manufacturer’s runtime table. Runtime does not fall in proportion: at half load you get more than twice the runtime of full load. How we measure and calculate it is on our page on UPS power and racks.
Offline, line-interactive or online
There are three designs, and they differ in what they do while the mains is present.
- Offline (standby). Switches to battery only when the power fails. Simple, and enough for a single till or one PC.
- Line-interactive. Also corrects high or low voltage without using the battery. The usual choice for most server cabinets in an office.
- Online (double conversion). Equipment always runs through the inverter, so there is no transfer moment. For sensitive equipment, an unstable supply or a generator whose output fluctuates.
Check the output waveform too: server power supplies work most reliably on a pure sine wave, and cheap units deliver an approximation. And choose a form factor that fits the cabinet: a rack-mount model of the right depth, or a tower beside it.
The link to the servers is half the work
A UPS that cannot tell the servers to shut down rides through the outage and then lets everything drop at once when the battery is empty. That is exactly what you wanted to avoid.
- The connection. Through a network card in the UPS or a USB cable to one server, with software on the hosts and the NAS that picks up the signal.
- The order. Applications and virtual machines first, then the hosts, and the storage last. The switch that carries the signal must stay up until the end.
- The way back. After the outage, start up in reverse order, with the server firmware set to power on when mains returns. Let the UPS wait until the battery has recharged enough, or a second outage finds you with empty batteries.
- The alert. Mains lost, battery nearly empty and battery due for replacement should reach someone, not just the display.
Test the whole chain once in an agreed window. Only then do you know it works.
The till and the branch
In a shop the question is different. The goal is usually not shutting down but finishing the sale: serving the customer at the till and letting the till close properly instead of dropping mid-transaction.
- What goes on it. The till PC or POS system, the receipt printer, and the router and switch the till communicates through.
- The card terminal. That belongs to the payment provider. Some have their own battery or a mobile connection; if it runs over the shop network, the router and switch must be on the UPS.
- What the software can do. Ask the POS supplier whether the till can keep selling offline and how it synchronises afterwards. That decides whether the connection matters during an outage.
- Where it sits. A small UPS under the counter gets heat, dust and feet. Place it where it gets air and will not be switched off by accident, and monitor it remotely if you have several branches.
How the till and a branch’s connection fit together is covered under POS and branch connectivity.
Batteries, self-tests and the annual trial
A UPS with worn batteries often shows no error until the moment it has to deliver. Three habits prevent that.
- Replace by date, not by failure. Lead-acid batteries last a limited number of years, and less in a warm cabinet. Note the installation date on the UPS and in the asset register, and plan the replacement ahead. Lithium batteries last longer, but they have a date too.
- Read the self-test, but do not rely on it blindly. A short self-test spots a dead battery, not always one that delivers only half.
- Run a real trial once a year. Under actual load, in an agreed window, using the UPS test function or by switching off the supply ahead of it. See how many minutes really remain and whether the shutdown starts on time.
Old batteries do not belong in general waste; return them through a battery collection scheme.
Where our work stops
What we do. We measure what is actually being drawn, agree the job and the minutes with you, choose the type and rating, and supply and install the UPS in the server cabinet or at the till. We connect the IT equipment, set up the shutdown and the alerts, test the chain and replace the batteries on time. We also tell you what supply the UPS needs.
What we do not do. We do no electrical work. A dedicated circuit, a hard-wired connection for a larger UPS, an external bypass switch, a generator and their inspection are work for a qualified electrician, in the UK to BS 7671. We pass the requirements on to that electrician and only connect once their work has been signed off. The card terminal belongs to the payment provider, and the infrastructure of the internet connection outside your building to the network operator.
Questions we get about this
The five that come up most often.
How many minutes of runtime does a server UPS need?
That follows from its job. If it must shut down cleanly, it is the delay plus the measured shutdown time plus a margin for ageing batteries. If it must bridge to a generator, it is the generator’s start and transfer time with a margin. There is no single figure that suits everyone.
What is the difference between VA and watts on a UPS?
A UPS has two limits: apparent power in VA and real power in watts. Equipment draws watts, so that is what you size on. Measure the actual draw rather than adding up the labels, and stay well below the watt limit so there is runtime left.
What kind of UPS do I need for a server rack?
For most office server cabinets, a line-interactive UPS with a pure sine wave output and a network card for the shutdown is the usual choice. An online double-conversion UPS suits sensitive equipment, an unstable supply or a generator. The rating and batteries follow from the measured load and the minutes needed.
How long do UPS batteries last?
Lead-acid batteries last a limited number of years, and less when they run warm; lithium batteries last longer. A worn battery often shows no error until it has to deliver. So replace by date and run a trial under real load once a year.
Do you also install the electrical circuit for the UPS?
No. We do no electrical work: a dedicated circuit, a hard-wired connection, a bypass switch, a generator and the inspection are work for a qualified electrician. We specify what the UPS needs, pass that on, and supply, install and configure the UPS itself once the electrical work has been signed off.
Further reading
What the UPS connects to.
Shall we work out your minutes?
Tell us what is in the server cabinet or under the counter and what must happen during an outage. We measure the load, calculate the minutes and tell you which UPS fits, and what the electrician needs to put in.
Practical IT knowledge in your inbox
New guides on management, security and the workplace, written by the people doing the work. No sales talk, and you can unsubscribe in one click.