Network cable testing and certification: what the test report tells you
Network cable testing can mean a simple box that lights up eight LEDs, or a certification tester that checks dozens of measurements per outlet against a standard. Only the second tells you whether a link does what the quote promised. This article covers which test gives which answer, what belongs in a test report and what to check at handover.
A continuity tester says whether the wires are in the right place, a qualification tester whether network traffic will run, and only a certification tester whether the link meets the standard.
At handover you test the permanent link, from patch panel to outlet, and every outlet, not a sample.
Keep the original test file alongside the PDF: it holds the margins, settings and calibration, and you will need them for a warranty claim or a fault.
Network cable testing: three kinds of tester, three answers
Someone who says the cabling has been “tested” can mean three very different things. Always ask which kind of tester was used.
- Verification. A simple tester checks that all eight conductors land in the right place at both ends with no shorts. Useful during installation, but it cannot see when conductors from two different pairs have been swapped in a way that keeps continuity intact. A split pair like that works at low speed and throws errors at higher speeds.
- Qualification. This tester checks whether a link can carry a given network speed, for example 1 or 10 Gbit. Useful for assessing existing cabling, but it is not a test against the cabling standard.
- Certification. A certification tester measures a set of electrical properties across the full frequency range of the category and sets each value against the limit in the standard. Only this result tells you a link is Cat6 or Cat6A, and only this is what manufacturers ask for before they issue a system warranty.
New cabling needs the third. The first two are tools for the installer and for fault-finding.
Permanent link or channel: what is actually measured
The standards define two test configurations, and a test report must say which one was used.
- The permanent link is the fixed part: from the patch panel port, through the cable in the wall or ceiling, to the outlet. No more than 90 metres. This is what the installer puts in and what should be tested at handover, using dedicated adapters that keep the tester’s own leads out of the measurement.
- The channel is the whole path from switch to device, including patch leads at both ends, no more than 100 metres in total. It tells you about the link as it is in use today, but as soon as someone swaps a patch lead it no longer applies.
So test the permanent link at handover, and supply good patch leads of the same category. A certified link with a cheap lead in front of it is, in practice, a link of that lead’s category.
What the test report contains
A test report has one line or one page per outlet. The terms come from the standard and look technical, but each measurement answers a plain question:
- Wire map: is every conductor in the right place, with no opens, shorts, reversed or split pairs?
- Length and propagation delay: how long is the link, how long does a signal take, and how much does that differ between the four pairs (delay skew)?
- Insertion loss: how much signal is lost along the way. Too long, too hot or poor cable shows up here.
- NEXT and PS NEXT: how much the pairs interfere with each other at the near end. Usually the first measurement to fail, often because a connector was untwisted too far.
- ACR-F and PS ACR-F: the same question at the far end.
- Return loss: how much signal reflects back, for instance from a kink, an over-tightened cable tie or a connector that does not match the cable.
- DC resistance and resistance unbalance: important for Power over Ethernet, where current runs over the pairs and uneven resistance between two conductors disturbs the signal.
Shielded cabling also needs a shield continuity check. And ask for a summary alongside the detail: how many links were tested, how many passed and which were retested after a fix.
Pass, marginal pass and the asterisk
A line marked PASS says every measurement stays within the limit of the standard. The report also says by how much: the margin, the gap between the worst measured value and the limit. A link that only just passes meets the standard today, but has little room for a lower-quality patch lead or a cable bundle that runs warmer later on.
A result with an asterisk, PASS* or FAIL*, means the measured value is so close to the limit that it falls within the tester’s measurement uncertainty. Whether such a result counts as a pass varies by manufacturer and by specification. Agree it before installation, not at handover.
Look at the spread as well. If many links pass the same measurement with a thin margin, there is often a common cause: the same installer, the same type of outlet, or a cable tray running past a warm room. That is worth a conversation even when everything is green.
The tester itself: calibration, adapters and the right standard
A test report is only as reliable as the way the testing was done. Four things that should be in the report, and that you can check without testing anything yourself:
- The selected limit. The tester compares each measurement with the limit the installer selected, for example the Class EA permanent link from ISO/IEC 11801 or Cat 6A from the TIA standard. A wrong choice, or a lower category, produces a PASS that says nothing about what you paid for.
- The cable type. Length is calculated from the speed of the signal in that specific cable. With the wrong type selected the length is wrong, and sometimes the result with it.
- Calibration. The tester’s serial number and the date it was last calibrated, within the interval set by the tester’s manufacturer. Its accuracy level must match the category: for Cat6A that is Level IIIe or higher under IEC 61935-1.
- Date, time and who tested. On every line, so the report belongs to the link and the moment.
Adapters also wear with every test. A worn adapter can fail a good link or, worse, pass a mediocre one. Ask how the installer keeps track of that.
When to have cabling tested
Testing is not only for new builds. Four moments when it saves money and fault-finding time:
- At handover: every fixed link, one hundred per cent, with the report as a condition of handover. For Cat6A the specification sometimes also asks for a sample test of interference between cables in the same bundle (alien crosstalk); agree whether that is included.
- After an extension or refurbishment: the new links, and existing ones wherever someone has worked in the ceiling or the tray.
- When a fault looks like the cable: a desk stuck at a lower speed, an access point that keeps restarting or a port with lots of errors. Test the link, and test the patch lead separately.
- When moving into an existing building: the cabling already in place often has no report. Before you put 10 Gbit or new PoE equipment on it, you are better off knowing what it can handle.
How the cabling is built up as a whole, from comms cabinet to desk, is on our page about structured cabling and the server rack.
What to keep at handover
The test report is the only evidence of the state of the cabling on the day it was handed over. Keep it so that someone can still use it years from now:
- The original test file, in the test software’s own format, alongside the PDF. It holds the full curves, margins and settings; a PDF often only the summary.
- Names that match the labels on the patch panel and outlets. A report running from “Test 1” to “Test 96” is useless after the first desk move.
- A floor plan and a patching schedule on which every outlet can be found.
- The manufacturer’s warranty certificate, if there is one. A system warranty is usually only issued when every link has been certified and the report accompanies the application; the conditions are the manufacturer’s own.
Where our work stops
What we do. We install data cabling, fit patch panels and outlets, and hand over every outlet with a certification report. We test existing cabling when you move into a building or suspect a fault in the cable.
What we do not do. The electrical installation belongs to the electrician: circuits, sockets in and around the comms cabinet, earthing and equipotential bonding of the building, and the inspection of all of that. With shielded cabling we connect the patch panel to the cabinet’s earth bar; that earth bar and everything behind it is put in by the electrician. Fire-stopping, walls and ceilings are building work, and we are not a building contractor. The system warranty on the cabling is given by the manufacturer, on its own terms.
Questions we get about this
The five that come up most often.
How do you test a network cable?
With a tester connected at both ends. A simple tester only checks that the conductors are wired correctly. A certification tester measures loss, crosstalk, reflection and resistance across the full frequency range, among other things, and compares each value with the limit in the standard for that category.
What is the difference between a permanent link and a channel test?
The permanent link is the fixed part from patch panel to outlet, no more than 90 metres, and is tested at handover. The channel is the whole connection from switch to device including patch leads, no more than 100 metres. A channel result no longer applies once a patch lead is replaced.
What does an asterisk after PASS mean in a test report?
That the measured value is so close to the limit in the standard that it falls within the tester’s measurement uncertainty. Whether such a result counts as a pass varies by manufacturer and by specification. Agree it beforehand, and look at the margin of the links that pass comfortably too.
Does every outlet need to be tested?
For new cabling, yes: every fixed link, not a sample. Otherwise a fault in one outlet only shows up when someone sits at that desk. Manufacturers also usually require a report covering all links before they issue a system warranty.
Do you also run the power supply to the comms cabinet?
No. Circuits, sockets, earthing and the inspection of the electrical installation are the work of a qualified electrician. We install the data cabling, test it and specify the power and earthing the cabinet needs, so the electrician can provide them.
Further reading
What cable testing connects to.
Shall we test your cabling?
Whether it is a new installation or a building with cable already in place, we test every outlet and hand over a report you can still read years from now.